Mayor Vincent C. Gray

Search
DC.gov   DDOT

 

between and go

DDOT Logo

District Department of Transportation


Office Hours
Monday through Friday, 8:15 am to 4:45 pm

How to Reach Us
55 M Street, SE, Suite 400
Washington, DC 20003
ddot@dc.gov

Phone: (202) 673-6813
Fax: (202) 671-0650
TTY: (202) 673-6813

FOIA Information
Agency Performance

Website: http://ddot.dc.gov
Blog: http://ddotdish.com

DDOT Facebook  DDOT Twitter  DDOT YouTube  DDOT Flickr  DDOT Scribd 


Terry Bellamy
Director

Ask the Agency

Calendar: Meeting Events
Civil Rights: Equal Opportunity
Contracts: Procurement

Note: This is an external feed that may load slowly when Twitter traffic is high.

 
Text Size: A A A

December 23, 2010

Pennsylvania Avenue Great Streets Project Update, December 2010 

The District Department of Transportation (DDOT) continues to make progress on the Pennsylvania Avenue Great Streets Project.

Story at a Glance 

Share Share   Printer-Friendly Version Print

 

  • A majority of the work has been completed between 27th Street and Branch Avenue.
  • The remaining roadway, sidewalk and curb/gutter reconstruction work in that area is anticipated to start in late Spring.

Media Contacts

(Washington, DC) The District Department of Transportation (DDOT) continues to make progress on the Pennsylvania Avenue Great Streets Project, a $30 million construction project east of the Anacostia River that is funded by the American Recovery and Reinvest­ment Act of 2009 (ARRA).

A majority of the work has been completed between 27th Street and Branch Avenue. The remaining roadway, sidewalk and curb/gutter reconstruction work in that area is anticipated to start in late Spring.

Upcoming Construction Activity

This is what residents and travelers can expect in the near future:

  • The utility relocation and storm drainage construction work taking place between Alabama Avenue and Fort Davis Drive will continue through early January. Starting Monday, December 27, through late January, this activity will proceed south from Fort Davis Drive to Southern Avenue.
  • Starting next week, weather permitting, water main installation work will take place between Alabama Avenue and Southern Avenue. This activity will take an estimated two month period to complete.

Impacts:

  • Curbside parking and lane restrictions will occur daily, Monday through Saturday, between 9:30 am and 3:30 pm.

DDOT will maintain three open travel lanes at all times. A reversible lane will ensure there are two lanes for peak traffic during rush hours, and one lane for traffic in the opposite direction.

Temporary signs and traffic control measures will be in place to alert and guide the traveling public through this area.

The Pennsylvania Avenue Great Streets project covers two miles of construction, from 200 ft. west of 27th Street to Southern Avenue. It will dramatically improve the physical character of the corridor and enhance transportation operations and safety for all users. The construction is scheduled to be completed in several phases over the next two (2) years.

To obtain more information about this project, you can visit our field office at 2410 Minnesota Avenue, SE or go online at www.greatstreetspennave.com. The contact for this project is DDOT’s Project Engineer Luan Tran at (202) 671-4649.

  • Some links provided on DC.Gov or other DC government websites may display vendor logos, banners, or similar identification. Such links are used for operational reasons only and do not constitute or imply any endorsement of any vendor or its product.